Eden Boys II

Client

The Secretary of State for Education

Duration

June 2018 – October 2018

Value

£300,000

Project introduction

The project involved extensive surveys of existing M&E plant. This included surveying the catering kitchen to ensure full compliance, together with the installation of heating and power.

How the work was delivered

The surveys led to the design and installation of heating and small power to some areas, repairs to existing plant rooms, gas boiler plant and rectification to all life systems.

Successes

The project brought new life to a redundant school, making it ready for students in the new fiscal year.

The project was fast-tracked and successfully completed alongside building fabric repairs which were carried out simultaneously.